Rehabilitation and Upgradation of “Section-I, Aurangabad-Sillod from km. 0+000 to km. 60+630 (Design Chainage) of Aurangabad–Jalgaon Road NH-753F” to Two lane with Paved Shoulder Configuration in the State of Maharashtra on EPC Basis
Project Details
| Value of Project |
INR 396.62 Crores |
| Location |
Aurangabad |
| State |
Maharashtra |
| Client |
MoRT & H |
| Award Date |
June 2017 |
| Expected completion by/th>
| April 2023 |
| Project Length |
48.13 Km |
| No.of Pipe Culverts |
55 Nos |
| No.of Box Culverts |
22 Nos |
| Minor Bridges |
19 Nos |
| Major Bridges |
4 Nos |
| Length of Drain |
24 Km |
| Length of Retaining Wall |
5.00 Km |
Major Quantity Details
| Earth Work |
8,65,347 Cum |
| Granular Sub Base |
1,45,470 Cum |
| Dry Lean Concrete(DLC) |
1,15,480 Cum |
| Pavement Quality Concrete (PQC) |
2,05,054 Cum |
| Structures Concrete |
1,07,244 Cum |