Scheme JNNSM Phase-1, Batch-1
| Installed Capacity |
5.116 MW, 21528 PV Modules (Multi Crystalline Solar Photo Voltaic Modules) |
| Total Area |
45.53 Acres |
| Effective Energy Generation |
KWh/KWp/year – Max9.198 Million Units/Year |
| Power Purchase Agreement |
25 Years from 05-07-2013 |
| Offtaker/Purchaser |
NTPC Vidyut Vyapar Nigam Limited (NVVN) |
| Neareast Railway Station |
Kadiri |
| Value of Project |
INR 70 Crores |
| Location |
Kadiri, Ananthpur Dist |
| State |
Andhara Pradesh |
| Client |
NTPC Vidyut Vyapar Nigam Limited |
| Award Date |
December 2010 |
| Completion Date |
|